A. Folino Construction provided a schedule for the PennDOT road reconstructionimpacting Allegheny Avenue and Allegheny River Boulevard within Verona and Oakmont Boroughs. All work will occur at night, starting at 6pm.
9.18 to 9.19: Milling/paving: Center Ave to College Ave
9.22: Milling: College Ave to Ann St
9.23 to 9.26: Road Base repairs, Center Ave to Ann St
9.29 to 10.2: Milling/Paving, Center Ave to Jones St & Ann St to Hulton Rd
10.3 to 10.8: Paving, Jones St to Hulton Rd
As posted earlier, A. Folino Construction will also be installing stormwater infrastructure, and milling, base repair, and paving on Washington Ave within this same timeframe. However, that construction work will be conducted during normal working hours.